Page 17 - Offshore Well Construction
P. 17

CHAPTER 13
                                                 Advances in Technology
        Petroleum Extension-The University of Texas at Austin



           HORIZONTAL DRILLING
           Horizontal drilling has become commonplace during the last decade and now covers the range of well types noted
           below. In general, horizontal wells are drilled in development areas where the formations and pressures are known.
           However, there is an extra time element required to plan and design a horizontal well—it will probably take twice as
           long to plan, design, and order the equipment items, and take approximately 50% extra time to drill. This is due to the
           additional cost of specialized equipment, safety constraints, and time taken to achieve the build along the horizontal
           leg. Also, the longer the horizontal section that needs to be drilled, the lower the build rate. The majority of horizontal
           wells are drilled using medium radius builds.


           Additional factors need to be considered when drilling a horizontal well, especially the need for primary well control
           where there is a greater requirement to maintain constant bottomhole pressure during a well kill. Hole cleaning is also
           more difficult due to the presence of ‘dune buildup’ across the build sections, and can also increase the chances of
           swabbing. Horizontal drilling has become the norm in many areas where the requirement is to maximize production.
           The current distance records are hampered only by the equipment limits of the respective drilling rigs, especially the
           hoisting capacity and maximum flow rates and pump capacity.


           Definition
           Horizontal drilling is the process of directing a drill bit to follow a horizontal path, approximately 90 degrees from
           vertical.


           Purposes

           Maximize production
           Enhance secondary production
           Enhance ultimate recovery
           Reduce the number of wells required to develop a field


           Main Types
           Short radius (1°–4°/1 ft) shallow wells, can go from vertical—horizontal in 50 ft
           Medium (8°–20°/100 ft) fractured reservoirs, need 300 ft to achieve build
           Long radius (2°–8°/100 ft) offshore, inaccessible reservoirs, need 1,500 ft
           Ultra short radius (almost no build)


           Applications
           Tight reservoirs (permeability < 1 md)
           Fractured reservoirs
           Economically inaccessible reservoirs
           Heavy oil reservoirs
           Channel sand and reef core reservoirs
           Reservoirs with water/gas coning problems
           Stratified thin reservoirs


                                                             13.1